Scott Osborn Ltd were awarded the Main Contract Landlords Works, which commenced May 2019.
The Phase 1 – Boiler House Works was completed on time and to programme by October 2019.
The Phase 2 – Common Area Works has begun and they will be working in the blocks through out this year. When these Block Works are being undertaken, you will not be permitted to carry out any works within your flat.
The Block Works will proceed in the following sequence:
Block 1 – January-April 2020
Block 2 – March-May 2020
Block 3 – May-July 2020
Block 4 – June-August 2020
Block 5 – August-October 2020
Block 6 – August-September 2020
Block 7 – September-October 2020